2011 Paving Program
Milling by: SJA Construction
Paving by: Cinnaminson DPW
Phase 1
Sylvania Avenue |
Entire Length 9/1 |
Villinger Avenue |
Cinnaminson Avenue to Broadwood Avenue 9/7-9/7 |
Curtis Road |
Entire Length 9/12 |
Orchard Way |
Entire Length 9/8 |
Susan Drive |
Branch Pike to Cambridge 9/8 |
Middlesex Drive Devon Road Walnut Place |
Entire Length Riverton Road to Wood Bridge 9/13,14 Entire Length 9/15,16 |
Phase 2
Andover Road |
Entire Length 9/20,21 |
Endicott Road |
New Albany Road to Andover Road 9/22 |
Brandies Court |
Entire Length 10/4 |
Willow Court |
Entire Length 10/5 |
Conrow Court Nassau Rd. |
Entire Length 10/6 Entire Length 9/26 |
Phase 3
Parry Road |
New Albany Road to Arbor Road 9/27,28 |
Plantation Drive |
Entire Length 9/30 |
Mount Vernon Drive |
Entire Length 10/3 |
Deerfield Road |
Entire Length 10/7 |
New Albany Road |
From Municipal Boundary to Just Past Pheasant Run 9/28 |
Garry Rd. |
10/1 |
There will be three (3) separate milling mobilizations as directed by the Township. Roadways within each phase of work are subject to change based on contractor scheduling and weather conditions. Milling phases have been set up by the Township to limit the roadways being exposed to weather conditions and to limit disturbance to residents for an extended period of time.
The first phase of milling took place August 29, 30 and 31. Paving commenced on Phase 1 on September 1st and will continue through September 16th. Door hangers will be provided for each phase of the milling and paving construction.
BRUSH: Please do not place brush curbside during the construction period.
REMOVE VEHICLES: Remove all vehicles from the road when notified to do so.
TRASH: All trash pick-up will follow the regular schedule.
UPDATES WILL BE PROVIDED REGULARLY AS PAVING PROCEEDS. PLEASE CHECK OUR WEB PAGE.
WE THANK YOU for your continued cooperation,
Your Friends at DPW